Schedule
| Permits | |
| Trench-Set Forms | |
| Plumbing- Rough/Inspection | |
| Concrete- Slab Preparation | |
| Termite Pretreat/Foundation Inspection | |
| Pour Slab | |
| Utility Trenching | |
| Pour Flatwork | |
| Frame Walls | |
| Trusses Delivered | |
| Sheetmetal Chase Top | |
| Frame Roof/Roof Nail Inspection | |
| Fireplace Set | |
| Plumbing – Top Out | |
| HVAC Rough In/Gutters | |
| Electric Wiring Rough-In | |
| Roof Material | |
| Paint – Fascia | |
| Windows Installed | |
| Exterior Doors Delivered/Set | |
| Frame Walk with Family | |
| Insulation Batts/Inspection | |
| Sheetrock/Nail/Inspection | |
| Clean – Sheetrock | |
| Stucco | ![]() |
| Sheetrock – Tape & Texture | |
| Garage Door Install | ![]() |
| Insulation – Blow In | |
| Set Cabinets & Trim | ![]() |
| Paint Interior/Exterior | ![]() |
| Downspouts | ![]() |
| Roof Trim | ![]() |
| Countertops | ![]() |
| Fireplace Surround & Hearth | ![]() |
| HVAC Finish | ![]() |
| Appliance Delivery | ![]() |
| Electric Finish | ![]() |
| Vinyl | ![]() |
| Plumbing Finish | ![]() |
| Carpet | ![]() |
| Finish Hardware | ![]() |
| Construction Clean | ![]() |
| Mirrors/Shower Doors | ![]() |
| Fireplace Doors | ![]() |
| Paint Touchup | ![]() |
| Envision Homes Pre-Home Demonstration | ![]() |
| Detail Punch List | ![]() |
| Final Clean | ![]() |
| Final Inspection | ![]() |

Driveway had to be widened and leveled in order to allow access to the homesite. (Also seen here: Family is currently living on site in trailers provided by FEMA.)

Rocks must be removed or crushed to make room for the new foundation.

Framing the new home.